(1) An owner or operator of a portable aggregate processing plant may not exceed 180 working days and may not exceed 365 calendar days at a single location. (2) An owner or operator of a portable aggregate processing plant may not operate the portable aggregate processing plant before 6 a.m. or after 10 p.m. each day at each temporary location. (3) An owner or operator of a portable aggregate processing plant shall operate in accordance with the terms and conditions of the Temporary Relocation Approval Letter issued by the director for each location. (4) An owner or operator of a portable aggregate processing plant shall comply with the applicable requirements of Rule R307-801, Utah Asbestos Rule.