WAC 296-150M-0815
WAC 296-150M-0815. What information must be included in a notice of correction?
When a contractor violates chapter 43.22 RCW, the department may issue a notice of correction which must contain the following:
(1) A description of the violation;
(2) A statement of what is required to correct the violation;
(3) The date by which the department requires corrections to be achieved; and
(4) Notice of the individual or department office that must be contacted to obtain a permit or other compliance information.