WAC 392-344-160
WAC 392-344-160. Acceptance of project by school district
The board of directors for a school district shall accept a project as complete or reject a project as incomplete after a review of the building commissioning final report, an inspection of the project, and receipt of certificate(s) of completion signed by the architect/engineer. A school district board resolution accepting the projects as complete must be submitted to OSPI before release of retainage shall be made in accordance with WAC 392-344-165 .