WAC 173-240-180. Approval of construction changes

Last amended: 2000Year: 2026Length: 46 wordsOfficial source
All wastewater facilities subject to the provisions of this rule must be constructed in accordance with the plans and specifications approved by the department. Any contemplated changes during construction, which are significant deviations from the approved plans, must first be submitted to the department for approval.