362 NLRB 621
OUTOKUMPU STAINLESS USA, LLC f/k/a THYSSENKRUPP STAINLESS USA, LLC
THYSSENKRUPP STAINLESS USA, LLC
621
ThyssenKrupp Stainless USA, LLC, a wholly owned
subsidiary of Outokumpu Stainless USA, LLC
and United Steel, Paper and Forestry, Rubber,
Manufacturing, Energy, Allied Industrial and
Service Workers International Union, AFL–
CIO, CLC. Cases 15–CA–070319 and 15–CA–
073053
April 22, 2015
ORDER DENYING MOTION1
BY CHAIRMAN PEARCE AND MEMBERS MISCIMARRA
AND HIROZAWA
The General Counsel seeks a default judgment in this
case pursuant to the terms of a settlement agreement.
The Union filed unfair labor practice charges on Decem-
ber 7, 2011, and January 24, 2012, alleging that the Re-
spondent violated Section 8(a)(3) and (1) by changing its
workplace discussion policy and enforcing it disparately;
engaging in surveillance and creating the impression of
surveillance; promulgating in writing an overly broad
“no-discussion during working hours policy” and disci-
plining two employees pursuant to that policy; and
threatening that employees would lose everything and
that collective bargaining would start from zero if the
Union were voted in. On April 30, 2012, the Union and
the Respondent entered into a settlement agreement re-
solving these charges.
Pursuant to the terms of the settlement agreement, the
Respondent agreed to post a settlement notice and to take
the affirmative actions described in the settlement
agreement and settlement notice. On May 7, 2012, the
Respondent emailed a letter to employees that discussed
its position regarding settling the charges (the “Side No-
tice”); the Respondent also posted the letter on its main
bulletin board. On May 17, 2012, the Respondent posted
the settlement notice on its main bulletin board and on
the Respondent’s intranet, where it remained until July
18, 2012. The settlement agreement contained the fol-
lowing performance clause:
The Charged Party agrees that in case of non-
compliance with any of the terms of this settlement
agreement by the Charged Party, and after 14 days
notice from the Regional Director of the National
Labor Relations Board of such noncompliance with-
out remedy by the Charged Party, the Regional Di-
rector will issue a complaint that will include the al-
legations spelled out above in the “Scope of Agree-
ment” section. Thereafter, the General Counsel may
file a motion for default judgment with the Board on
1 The National Labor Relations Board has delegated its authority in
this proceeding to a three-member panel.
the allegations of the complaint. The Charged Party
understands and agrees that all of the allegations of
the complaint will be deemed admitted and it will
have waived its right to file an answer to such com-
plaint. The only issue that may be raised before the
Board is whether the Charged Party defaulted on the
terms of this settlement agreement. The Board may
then, without necessity of trial or any other proceed-
ing, find all allegations of the complaint to be true
and make findings of fact and conclusions of law
consistent with those allegations adverse to the
Charged Party on all issues raised by the pleadings.
The Board may then issue an order providing a full
remedy for the violations found as is appropriate to
remedy such violations. The parties further agree
that a U.S. Court of Appeals Judgment may be en-
tered enforcing the Board order ex parte, after ser-
vice or attempted service upon Charged Par-
ty/Respondent at the last address provided to the
General Counsel.
On September 19, 2012, the Region informed the Re-
spondent that its Side Notice constitutes noncompliance
with the settlement agreement. The Region and the Re-
spondent discussed the Region’s proposed remedial steps
to address the alleged noncompliance, but the Respond-
ent declined to comply with the Region’s ultimate re-
quirement that it repost the Board’s notice for an addi-
tional 60 days to remedy its alleged breach. On March
27, 2013, the Region notified the Respondent that it
would reinstate the charges if the Respondent did not
repost the settlement notice for 60 days. The Respondent
did not respond.
Accordingly, on June 28, 2013, the Regional Director
issued an order consolidating cases, consolidated com-
plaint, and notice of hearing. The Respondent filed a
timely answer. On August 15, 2013, the Respondent
filed a Motion for Summary Judgment arguing that the
complaint should be dismissed because it had neither
failed to comply with the settlement agreement nor en-
gaged in postsettlement unfair labor practices. On No-
vember 22, 2013, the Board denied the Respondent’s
motion.
On September 29, 2014, pursuant to the performance
clause in the settlement agreement, the General Counsel
filed this Motion for Default Judgment, along with a
supporting brief asserting that the Respondent had de-
faulted on the terms of the settlement agreement. On
October 1, 2014, the Board issued an Order Transferring
Proceeding to the Board and Notice to Show Cause why
the motion should not be granted. On October 15, 2014,
the Respondent filed a response and memorandum in
362 NLRB No. 71
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
622
opposition to the Motion for Default Judgment, disputing
the allegation that the settlement agreement had been
breached.
Having duly considered the matter, we find that default
judgment is not appropriate under the circumstances of
this case because, based on the conflicting representa-
tions of the parties, genuine issues of material fact exist
which prevent a final determination as to whether the
terms of the settlement agreement have been breached.2
2 In denying the Respondent’s Motion for Summary Judgment, we
noted that the “propriety of setting aside the settlement agreement” was
Accordingly, we deny the General Counsel’s Motion
for Default Judgment and remand this proceeding to the
Regional Director for Region 15 for further appropriate
action.
“an issue for the judge to decide in the first instance, based on a more
complete record regarding, for example, the posting of the notice and
letter, and the Respondent’s compliance with the affirmative settlement
terms.”
Having denied the General Counsel’s Motion for Default Judgment,
we similarly deny his motion to strike the Respondent’s July 11, 2013
answer, without prejudice to the General Counsel raising the motion
before the judge, if appropriate, after the judge rules on the alleged
breach of the settlement agreement.