35 Ill. Adm. Code 820.302
General Operating Standards
Section
820.
302Â General
Operating Standards
a)Â Â Â Â Â Â Â Â Compliance
with Local Requirements. GCDD
recovery facilities
are
subject to
local zoning, ordinance, and land use requirements
. [415 ILCS 5/22.38(a)]
b)Â Â Â Â Â Â Â Â Location
Standards. GCDD
recovery facilities
must
be located in
compliance
with local zoning requirements or, in the absence of local zoning requirements,
must
be located so that no part of the
GCCD recovery
facility
boundary is closer than 1,320 feet from the nearest property zoned primarily
for residential use
. [415 ILCS 5/22.38(a)]
c)Â Â Â Â Â Â Â Â Minimum
Recycling Rate. The owner or operator of a GCDD recovery facility must
ensure
that no less than 40% of the total
GCDD
received at the facility on a
rolling 12-month average basis is recyclable
GCDD. [415 ILCS
5/22.38(b)(0.5)]Â For purposes of this subsection (c), GCDD is measured by
weight.
d)Â Â Â Â Â Â Â Â Operating
Hours
1)Â Â Â Â Â Â Â Â GCDD may
be received at the GCDD recovery facility only during operating hours
established by a permit issued under this Part.
2)Â Â Â Â Â Â Â Â If a
GCCD recovery facility receives GCDD outside of permitted operating hours to
respond to an emergency, then the GCCD recovery facility operating records must
maintain a written record of the date, time, and reason the GCDD recovery facility
received the GCDD. The owner or operator must also notify the Agency’s
Regional Office responsible for inspecting the GCDD recovery facility on the
next operating day within the GCDD recovery facility's permitted operating
hours.
3)Â Â Â Â Â Â Â Â If
the emergency requires receiving GCDD outside of permitted operating hours for
more than one day, then the owner or operator of the GCDD recovery facility must
obtain prior approval from the Agency to extend emergency operating hours
beyond the first day.
e)Â Â Â Â Â Â Â Â Equipment.Â
Equipment necessary to achieve and maintain compliance with this Part must be
maintained and available for use at the facility during all hours of operation.
f)Â Â Â Â Â Â Â Â Utilities.Â
All utilities, including electricity, heat, interior and exterior lighting, and
communications equipment, necessary to operate in compliance with the
requirements of this Part, must be available at the facility at all times.
g)Â Â Â Â Â Â Â Â Maintenance.Â
Adequate shelter, sanitary facilities, and emergency communications for
employees must be maintained at the GCDD recovery facility at all times.
h)Â Â Â Â Â Â Â Â Dust
Control. Wind dispersal of particulate matter must be prevented.
i)Â Â Â Â Â Â Â Â Â Fire
Protection. Equipment necessary to respond to fires and provide emergency
notifications to the nearest fire department must be maintained at the GCDD
recovery facility.
j)Â Â Â Â Â Â Â Â Â Vehicle
Safety Measures
1)Â Â Â Â Â Â Â Â The
GCDD recovery facility must maintain roads and traffic flow patterns adequate
for the type and weight of traffic using the facility and onsite equipment.
2)Â Â Â Â Â Â Â Â The
GCDD recovery facility must maintain sufficient area to minimize traffic
congestion, provide for safe operation, and allow for queuing of hauling
vehicles.
3)Â Â Â Â Â Â Â Â The
GCDD recovery facility must use safety mechanisms to prevent vehicles from
backing into fuel storage tanks, equipment, or other structures.
k)Â Â Â Â Â Â Â Â Surface
Water Drainage. Measures to ensure surface water drainage is diverted from
areas where GCDD or other materials are stored must be implemented at the
facility. Surface water drainage must be controlled so adjacent properties are
not adversely impacted.
l)Â Â Â Â Â Â Â Â Â Run-on
and Run-off Control
1)Â Â Â Â Â Â Â Â The
owner or operator must operate the facility in a manner that prevents exposure
of any materials to run-on or run-off.
2)Â Â Â Â Â Â Â Â Run-off
from roadways and parking areas must be controlled using storm sewers or must
be compatible with natural drainage for the facility.
3)Â Â Â Â Â Â Â Â Run-off
from roadways and parking areas must not carry GCDD, CCDD, waste, or any of
their constituents to soil, surface water, or groundwater.
m)Â Â Â Â Â Â Â Boundary
Control
1)Â Â Â Â Â Â Â Â Access
to the GCDD recovery facility must be restricted to prevent unauthorized
entry.
2)Â Â Â Â Â Â Â Â The
GCDD recovery facility must post at the entrance to the GCDD recovery facility
stating, at a minimum:
A)Â Â Â Â Â Â Â that
the
GCDD recovery
facility only accepts GCDD;
B)Â Â Â Â Â Â Â the
GCDD recovery facility’s permit number;
C)Â Â Â Â Â Â Â the
GCDD recovery facility’s hours of operation;
D)Â Â Â Â Â Â Â the
penalty for unauthorized trespassing and dumping;
E)Â Â Â Â Â Â Â the
name and telephone number of the appropriate emergency response agency or
agencies to deal with emergencies and other problems; and
F)Â Â Â Â Â Â Â Â the
name, address, and telephone number of the GCDD recovery
facility’s
operator.
n)Â Â Â Â Â Â Â Â Contingency
Plan
1)Â Â Â Â Â Â Â Â The
owner or operator of a GCDD recovery facility must establish and maintain a
Contingency Plan that:
A)Â Â Â Â Â Â Â minimizes
the hazards to human health and the environment from fires and run-off of
contaminants resulting from a fire at the GCDD recovery facility;
B)Â Â Â Â Â Â Â is
carried out immediately whenever there is a fire;
C)Â Â Â Â Â Â Â describes
the actions GCDD recovery facility personnel must take in response to fires and
run-off resulting from fires;
D)Â Â Â Â Â Â Â minimizes
the hazards to human health and the environment from vectors and other nuisance
organisms that may breed or be present at the GCDD recovery facility;
E)Â Â Â Â Â Â Â minimizes
the hazards to human health and the environment from flooding in the event of a
100-year flood. The GCDD recovery facility must not restrict the flow of a
100-year flood, or reduce the temporary water storage capacity of the 100-year
floodplain, unless measures are taken to provide alternative storage capacity.
F)Â Â Â Â Â Â Â Â describes
evacuation procedures, including evacuation signals, primary evacuation routes,
and alternate evacuation routes to be used when the primary routes could be
blocked;
G)Â Â Â Â Â Â Â contains
an up-to-date emergency equipment list that identifies all emergency equipment
at the GCDD recovery facility, such as fire-extinguishing systems,
fire-suppression material, spill-control equipment, decontamination equipment, and
communication and alarm systems, and describes the physical location and
capabilities of each listed item; and
H)Â Â Â Â Â Â Â includes
the name, address, and telephone number of an employee designated as the
primary emergency coordinator responsible for coordinating emergency response
measures at the GCDD recovery facility, as well as an up-to-date list of all
alternate emergency coordinators, listed in the order they will assume
responsibility for coordinating emergency response measures at the GCDD
recovery facility if the primary emergency coordinator or another alternate
emergency coordinator is unavailable.
2)Â Â Â Â Â Â Â Â The
owner or operator must submit a copy of the contingency plan, and all revisions
to the plan, to the local fire department and keep a copy of the same on-site
for review by the Agency. The owner or operator must keep in the operating
record documentation demonstrating that the plan and all plan revisions have
been submitted to the fire department.