77 Ill. Adm. Code 855.470
Clearance Air Monitoring and Analysis
Section 855
Section 855.470Â Clearance
Air Monitoring and Analysis
a)Â Â Â Â Â Â Â Â Following the completion of Section 855.465, cleanup
procedures, the contractor shall notify the project manager that contained
areas are ready for clearance air monitoring.
b)Â Â Â Â Â Â Â Â The project manager shall conduct a visual inspection of the
contained area. Â The project manager shall document the findings of the
inspection. If the project manager finds the contained area to be clean, he or
she shall then arrange for the air sampling professional to sample the air in
the work area and adjacent areas for airborne fiber concentrations. The air
sampling professional shall conduct clearance air monitoring as explained in
this Section.
c)Â Â Â Â Â Â Â Â Sampling shall not begin until at least 12 hours after wet
cleaning has been completed. Air sampling may not be conducted unless all
surfaces in the contained area are dry.
d)Â Â Â Â Â Â Â Â The HEPA filtered negative air pressure equipment shall be in
operation in the contained area during clearance air monitoring.
e)Â Â Â Â Â Â Â Â The air sampling procedures and analysis shall be conducted in
accordance with Asbestos Hazard Emergency Response Act (AHERA) (40 CFR 763) and
Section 855.170(b)(1) requirements.
f)Â Â Â Â Â Â Â Â Air sampling equipment shall be placed randomly in the work
areas, but shall not be placed in corners of rooms or near obstructions.
g)Â Â Â Â Â Â Â Â The following aggressive sampling techniques shall be used
during all clearance air monitoring:
1)Â Â Â Â Â Â Â Â Before sampling begins, the exhaust from forced air equipment
(such as a one horsepower leaf blower) shall be directed against all walls,
ceilings, floors, ledges and other surfaces in the room. This procedure
requires at least five minutes per 1,000 sq. ft. of floor.
2)Â Â Â Â Â Â Â Â 20-inch fans shall be used for air circulation during the
sampling procedure. The fan exhaust shall be directed toward the ceiling. The
fans shall be operated on the lowest speed setting. Fans shall be operated in
the center of each room where sampling will take place. At least one fan per
10,000 cubic feet of room space shall be used.
h)Â Â Â Â Â Â Â Â The air sampling professional shall report the clearance air
monitoring results in writing to the project manager.
i)Â Â Â Â Â Â Â Â Â If the air sampling results indicate a concentration of
airborne asbestos fibers in excess of AHERA clearance criteria (70 structures
per millimeter squared), the contractor shall re-clean the contained area. The
contractor shall not be released until the contained area meets AHERA clearance
criteria.