10 CSR 26-2.036
Operation and Maintenance Walkthrough Inspections
PURPOSE: This rule contains the new
requirements for walkthrough inspections of
underground storage tank systems.
PUBLISHER’S NOTE: The secretary of state
has determined that the publication of the
entire text of the material which is incorporated by reference as a portion of this rule would
be unduly cumbersome or expensive. This
material as incorporated by reference in this
rule shall be maintained by the agency at its
headquarters and shall be made available to
the public for inspection and copying at no
more than the actual cost of reproduction.
This note applies only to the reference material. The entire text of the rule is printed here.
(1) To properly operate and maintain underground storage tank (UST) systems, owners
and operators must ensure the following
requirements are met:
(A) Owners and operators must ensure
walkthrough inspections are conducted as follows:
1. Spill prevention equipment must be
checked at least once every thirty (30) days,
or prior to each delivery for USTs that
receive deliveries less frequently than once
every thirty (30) days. The person(s) conducting the inspection must visually check for any
damage, remove liquid or debris, check for
and remove obstructions in the fill pipe,
check the fill cap to make sure it is securely
on the fill pipe, and for double-walled spill
prevention equipment using interstitial monitoring, check for a leak in the interstitial
area; and
2. Release detection equipment must be
checked at least once every thirty (30) days.
The person(s) conducting the inspection must
check to make sure the release detection system is operating with no alarms or other
unusual operating conditions present and
ensure records of release detection testing are
reviewed monthly and are current;
(B) At least annually, owners and operators
must ensure the following is done:
1. Containment sumps required in 10
CSR 26-2.020 or 10 CSR 26-2.021, including tank top or submersible turbine pump,
under-dispenser, and transition or intermediate sumps, must be visually checked for any
damage, leaks to the containment sump area,
or releases to the environment; liquid or
debris must be removed; and the interstitial
space of double walled containment sumps
must be checked for leaks; and
2. Tank gauge sticks or other hand held
release detection equipment must be checked
for operability and serviceability;
(C) The first walkthrough inspections in
this section are due—
1. Immediately upon installation for new
UST systems installed after July 1, 2017; or
2. No later than January 1, 2020, for
existing UST systems;
(D) Owners and operators may use the following codes to comply with this rule:
1. Petroleum Equipment Institute RP 50011, Recommended Practices for Inspection and
Maintenance of Motor Fuel Dispensing
Equipment. This document is incorporated by
reference without any later amendments or
modifications. To obtain a copy, contact the
Petroleum Equipment Institute, Box 2380,
Tulsa, OK 74101-2380, (918) 494-9696,
www.pei.org;
2. Petroleum Equipment Institute RP
900-08,
Recommended
Practices
for
Inspection and Maintenance of UST Systems.
This document is incorporated by reference
without any later amendments or modifications. To obtain a copy, contact the Petroleum
Equipment Institute, Box 2380, Tulsa, OK
74101-2380, (918) 494-9696, www.pei.org;
and
3. Another method approved by department, including code(s) of practice developed
by a nationally recognized association(s) or
independent testing laboratory(ies), determined to be no less protective of human
health and the environment than the requirements listed in this rule; and
(E) Owners and operators must maintain
records (in accordance with 10 CSR 262.034) of the inspections required by this rule
for one (1) year. The record must include a
list of each area checked, whether each area
checked was acceptable or needed action, and
a description of any actions taken as a result
of the inspection.
AUTHORITY: sections 319.105, 319.107, and
319.137, RSMo 2016.* Original rule filed
Aug. 15, 2016, effective May 30, 2017.
*Original authority: 319.105, RSMo 1989; 319.107, RSMo
1989, amended 1994; and 319.137, RSMo 1989, amended
1993, 1995, 2004.