NDAC 43-02-02.2-49
Excursions - Verifying analysis
Cite as N.D. Admin. Code ยง 43-02-02.2-49
1.
If a routine sample analysis ("initial sampling") indicates a control parameter is exceeding its
upper level value in a monitoring well, the operator shall complete a verifying analysis
("second sampling") of samples taken from the affected well and the monitoring wells adjacent
to the affected well. The operator shall take the second sampling within two working days after
being notified by the laboratory of the initial sampling results. If the results from the first and
second sampling event both indicate an excursion has occurred, then an excursion is
considered verified for the purpose of initiating remedial action in accordance with section
43-02-02.2-51. If the results of the second sampling are not complete within seven days after
the initial sampling event that indicated an excursion might be present, the excursion will be
considered verified.
2.
If the results from the first and second sampling events provide conflicting information about
whether or not an excursion has occurred, then a third sampling event must be conducted
within two working days after receipt of the results from the second sampling event. If the
results of the third sampling are not complete within seven days after the second sampling
event, the excursion will be considered verified.
3.
All sample analyses results for excursion events must be submitted to the department within
two business days after the operator receives them.