OAR 860-084-0170
OAR 860-084-0170. Distributing Solar Photovoltaic Pilot Capacity by Electric Company
(1) Each electric company will receive a share of the total solar photovoltaic pilot program capacity as established by Commission order.
(2) An electric company may not solicit or accept additional capacity reservations for a solar photovoltaic pilot program once the company reaches 100 percent of its allocated solar photovoltaic pilot capacity limit.
(3) The Commission may consider requests to adjust each electric companyโs solar photovoltaic pilot capacity limit by changing the allocation of the total solar photovoltaic pilot program capacity from those established at pilot program initiation.